← All client results Case study · HH, kVA & capacity

From 1,000 kVA to 70 kVA.

How a review of 24 months of maximum-demand data led to a major reduction in Authorised Supply Capacity for an anonymised UK manufacturing business.

UK manufacturing business HV electricity supply SP Energy Networks Completed June 2026
Data reviewed 24 months Maximum-demand and authorised-capacity history supplied by the DNO.
Recent 12-month peak 41 kVA Jun 2025–May 2026. Average monthly maximum demand over the same period was 29.2 kVA.
Capacity removed 930 kVA Reduction from the 1,000 kVA capacity in place at the time of review.
Effective date 1 Jun 2026 Date the DNO confirmed the new 70 kVA capacity would apply from.
01 The problem

The reserved capacity had moved a long way from the site's actual demand.

This was not a supplier unit-rate exercise. The issue sat in the network charging structure: the site was carrying 1,000 kVA of Authorised Supply Capacity while its recorded demand was materially lower.

01

We asked the DNO for the underlying data.

Smart Energy requested the previous 24 months of maximum-demand figures, the current authorised capacity, the site's HV/LV status and confirmation that the correct Line Loss Factor tariff was being applied.

02

The supply was confirmed as HV.

SP Energy Networks returned the demand and capacity history and confirmed that the site was already on the lowest applicable HV LLF/tariff. That meant there was no lower LLF band to pursue.

03

The ASC rose sharply while the site's demand stayed low.

The DNO data showed 100 kVA of authorised capacity in June and July 2024, 500 kVA from August 2024, then 1,000 kVA from May 2025. The month the ASC moved to 1,000 kVA, recorded maximum demand was just 29 kVA. Across the final 12 months reviewed, monthly maximum demand averaged 29.2 kVA and never exceeded 41 kVA.

04

A reduction to 70 kVA was requested.

After reviewing the demand pattern and the client's position, Smart Energy asked the DNO to reduce the Authorised Supply Capacity to 70 kVA. The DNO approved and processed the change.

02 What the data showed

The recent demand profile was nowhere near 1,000 kVA.

The full 24-month record included one higher reading of 84 kVA in November 2024, followed by 60 kVA in December 2024. From January 2025 through May 2026 — 17 consecutive monthly readings — maximum demand never exceeded 41 kVA. Over the final 12 months reviewed, the monthly maximum averaged 29.2 kVA against an ASC of 1,000 kVA.

Jun–Jul 2024 100 kVA Recorded maximum demand was 7 kVA and 9 kVA in these two months.
Aug 2024 500 kVA ASC increased to 500 kVA. The 24-month historical high of 84 kVA occurred later, in November 2024.
May 2025 1,000 kVA ASC doubled again even though that month's recorded maximum demand was 29 kVA.
Jun 2026 70 kVA Approved after the recent 12-month profile showed a 41 kVA maximum and 29.2 kVA average monthly peak.
03 The timeline

From enquiry to approval.

The case moved quickly because the request went directly to the network operator with a valid Letter of Authority and a specific set of technical questions.

Smart Energy requested the capacity and demand history.

The request covered 24 months of maximum demand, current ASC, connection level and whether the LLF classification could be improved.

SP Energy Networks returned the data.

The DNO confirmed the HV supply, supplied the demand/capacity history and confirmed the customer was already on the lowest possible applicable HV tariff.

Smart Energy requested 70 kVA.

The reduction request was made directly back to the DNO after reviewing the returned capacity and maximum-demand information.

The reduction was approved and processed.

SP Energy Networks confirmed the new Authorised Supply Capacity at 70 kVA, effective from 1 June 2026, and advised that the supplier would also be informed.

How the saving was calculated

£33,945 a year — with the calculation shown.

The DNO confirmed the physical change in capacity. The financial saving is Smart Energy's annualised calculation using the capacity charge applying to the client's account when the review was completed.

Capacity removed 1,000 kVA − 70 kVA = 930 kVA
Capacity rate used 10p per kVA per day The rate applying to the client's account at the time of the review.
Annualised calculation 930 × £0.10 × 365 = £33,945 Annualised figures depend on the capacity charging rate continuing at the level used in the calculation.
05 The outcome

A network cost issue that would not have been solved by simply finding a cheaper supplier.

The case shows why a commercial electricity review can need to go beyond unit rates and standing charges. The site's network capacity had to be checked against real demand before the saving could be identified.

The 70 kVA figure was below the single 84 kVA reading recorded in November 2024, but the subsequent demand profile was materially lower: no monthly maximum exceeded 41 kVA from January 2025 through May 2026. That more recent operating pattern formed part of the review before the 70 kVA request was made and approved.

SP Energy Networks also warned that surrendered capacity may not automatically be available again in future and could require network reinforcement and associated costs. Capacity reductions therefore need to be considered against the site's future operational requirements, not treated as an automatic exercise.

The useful question was not “who is the cheapest supplier?” It was “why is this site carrying 1,000 kVA of authorised capacity?”

That distinction matters. Procurement is one part of commercial energy management; metering, network charges and site configuration can create costs that supplier-price comparisons alone will never find.

Case-study disclosure

The client's identity, MPAN, contact details and precise site information have been withheld for commercial confidentiality. Technical figures are taken from the completed review and DNO correspondence. The £33,945 figure is an annualised calculation based on the capacity charge applying when the review was completed; it is not a supplier or DNO guarantee of future charges.

06 Review your supply

Is your agreed capacity still right for the way your site operates?

We can review Half-Hourly demand, authorised capacity and the wider metering setup to see whether the current configuration still makes commercial sense.